Callide Power Station

Coal-fired power station in Australia

  • CS Energy
Thermal power station Primary fuelCoalTurbine technologySteam turbinesCooling sourceFreshPower generation Units operational8Nameplate capacity1,720 MW
[edit on Wikidata]

Callide Power Station is an electricity generator at Mount Murchison, Shire of Banana, Queensland, Australia. It is coal powered with eight steam turbines with a combined generation capacity of 1,720 megawatts (MW) of electricity. Callide A was commissioned in 1965, refurbished in 1998 and decommissioned in 2015/16.[2] As of 2018, generation capacity was 1510 MW.[2]

The coal for Callide comes from the nearby Callide Coalfields and water from the Awoonga dam and Stag Creek Pipeline.[3]

An explosion and fire at the Callide C power plant in late May 2021 caused a significant power outage that affected over 375,000 premises and raised electricity prices for weeks afterwards.

November 2022 all four units at the coal-fired Callide Power Station were not operating after a structural failure at the cooling plant brought the C3 unit offline, and later on the B2 unit tripped during scheduled testing, followed by the last unit, B1, also tripping.[4][5]

CS Energy owns 100 per cent of Callide A and Callide B, and owns Callide C in a 50/50 joint venture with IG Power.

Callide A

Premier Frank Nicklin opening Callide Power Station, 21 August 1965

At the end of 1962 approval was granted for a new power station near Biloela.[6] Work commenced at the site in February 1963. The design of the plant based around separate generating units and a control room was a first for Queensland.[6] It was also the first power station in Queensland to use dry cooling towers.[6]

Callide Oxyfuel Project, 2012

It had four 30 MW steam turbines, the first of which was operating by June 1965. From its commissioning a drought meant water restrictions at the station reduced output.[6] The second set was expected to be operating by May 1966, but was lost at sea while being transported from England.[6] A replacement unit arrived in June 1967. The third set was operating in October 1967 and the fourth in May 1969.[6] The total cost of the project was A$28.7 million.[6]

Callide A has been in storage since 2001, except for Unit 4 which was being used for the Callide Oxyfuel project.[7] The Callide Oxyfuel project was decommissioned in 2015/16 after demonstrating carbon capture technology for two years.[2]

Callide B

Following on from an aggressive construction program at Tarong Power Station, Callide B was commissioned in 1988 with two 350 MW steam turbines. The Hitachi machines are almost identical to those in Tarong and Stanwell.

In October 2019, Federal Energy Minister Angus Taylor announced that Callide B's originally planned 2038-39 closure was being brought forward to 2028.[8]

Callide C

The Callide Power Plant (a.k.a. Callide C) was commissioned in 2001 with two 405 MW advanced cycle steam turbines.[9] Callide C uses a more efficient "supercritical" boiler technology to burn coal to generate electricity.[10] It was built to operate to 2050.[11]

Carbon Monitoring for Action estimates this power station emits 5.73 million tonnes of greenhouse gases each year as a result of burning coal.[12] The Australian Government introduced a Carbon Pollution Reduction Scheme in 2011 to help combat climate change, intended to reduce emissions from power stations. The scheme was replaced in 2014 by a 'direct action' program. The National Pollutant Inventory provides details of other pollutant emissions, but, as at 23 November 2008, not CO2.[13]

On 25 May 2021, an explosion and subsequent fire at Callide C caused a significant power outage (including Callide B and parts of Stanwell and Gladstone power stations)[14] that affected over 375,000 premises,[15][16][17] and caused increased power prices for weeks.[18] The hydrogen-filled generator had a catastrophic failure, resulting in significant damage. Despite speculation that the plant would close, it was repaired at an estimated cost of $200M and reoponed in April 2024.[19]

The coverup continues who is “Shift Change” ? Are you the technical editor contracted to CS Energy?

The simple fact is unit C4 was forced out of service by Ignorance

1/ A HV Switching was carried out without informing the unit C4 unit operator.

2/ The 220V Critical Battery Supply was disconnected from the unit 220V DC.

3/ The Insurance has refused the $300M claim by CSEnergy.

4/ The RTS insurance is self insurance as nobody is prepared to provide cover.

5/ The cost of rebuilding is to be covered by the QLD government.

6/ Stop the coverup and return the C4 Unit to service.

Queensland’s embattled Callide Power Station has been crippled by industrial action amid an enterprise agreement dispute, as a fierce political blame game continues over the cause of a 2021 catastrophic blaze at the state-owned facility. The Mining and Energy Union chapter of the CFMEU said workers would limit productivity and ‘‘ grind things down’ ’ at the central Queensland site run by state-owned corporation CS Energy, warning that ongoing action in the coming days would ultimately risk increasing energy prices. The union’s state vice-president , Shane Brunker, said workers were calling for fair redundancy provisions and career transition support ahead of the power station’s planned partial closure in 2027. He said the lack of career development opportunities had frustrated staff, given the state government’s repeated claims that it would provide transition pathways as it moves away from a reliance on coal and embarks on an ambitious transition to renewable energy. The state has committed to an emissions reduction target of 75 per cent on 2005 levels by 2035, with 80 per cent of the grid to be powered by renewable energy by the same time. ‘‘ We need training so these workers, when they go on to the open market, are attractive,’’ Mr Brunker told The Australian Financial Review. ‘‘ CS Energy is just contracting everything out – there’s supervisory roles or career progression [that our workers don’t get an opportunity] to go into because they just want to bring contractors in and appoint contractors over the top of permanent workers.’’ The industrial action comes after a damning internal review into the plant’s explosion more than three years ago blamed a failure of management to understand technical risks. It also cited an alarming backlog in maintenance at the power station run by CS Energy and its joint-venture partners. This is despite repeated assurances from Queensland Labor ministers, who provided guarantees to parliament in the last three years that the upkeep concerns did not play a part in the fire , which left about half-a-million homes without power and led to a surge in electricity prices. Energy Minister Mick de Brenni, a shareholding minister of CS Energy, rejected assertions of this nature in the days after the explosion: ‘‘ We can guarantee all of the maintenance work that is required to be done on all of our power stations has been done.’’ The revelation of the maintenance concerns in the draft report from forensic engineer Sean Brady turned the blowtorch on to Mr de Brenni, with the LNP opposition demanding his resignation . But the minister yesterday blamed senior members of the CS Energy board who have since been replaced, most notably the former chairman – and former Labor Brisbane lord mayor – Jim Soorley. ‘‘ I relied on advice {that was provided to me by the CEO and the chair on the date of that incident,’’ Mr de Brenni said. ‘‘ The CEO provided me incorrect advice. The board and the chair provided me incorrect advice. ‘‘ Dr Brady’s report makes it very clear, in terms of the incident on the day and the matters leading up to that. . . those individuals involved in that, leading that organisation, are no longer with CS Energy.’’ Mr Brunker said workers had been vindicated by the review findings and that CS Energy and the government had ‘‘ to wear some of the criticism’’ . ‘‘ It’s come out in the report they were forcing cost-cutting , and cost-cutting only means one thing when you’ve got critical infrastructure – shortcuts will lead to disaster, catastrophic failures,’’ he said. Copyright © 2024 Australian Financial Review

Richard Baum.


See also

  • flagQueensland portal

References

  1. ^ "Callide Power Station". Retrieved 24 March 2022.
  2. ^ a b c "Callide Power Station". Archived from the original on 2 October 2018. Retrieved 2 October 2018.
  3. ^ InterGen Archived 2008-08-05 at the Wayback Machine page on Callide. Retrieved 2008-05-18
  4. ^ Hines, Jasmine; Culliver, Paul (4 November 2022). "Callide Power Station in central Queensland completely offline". ABC News. Australian Broadcasting Corporation. Retrieved 4 November 2022.
  5. ^ Loftus, Tobi; Culliver, Paul (1 November 2022). "'Structural failure' at Callide Power Station near Biloela leaves unit offline". ABC News. Australian Broadcasting Corporation. Retrieved 4 November 2022.
  6. ^ a b c d e f g Dunn, Col (1985). The History of Electricity in Queensland. Bundaberg: Col Dunn. pp. 136–139. ISBN 0-9589229-0-X.
  7. ^ Spero, Chris; Yamada, Toshihiko; Nelson, Peter; Morrison, Tony; Bourhy-Weber, Claire. "Callide Oxyfuel Project – Combustion and Environmental Performance" (PDF). www.eventspro.net. 3rd Oxyfuel Combustion Conference. Retrieved 5 May 2017.[permanent dead link]
  8. ^ "Qld to close coal-fired power station a decade early". Australian Financial Review. 6 October 2019. Archived from the original on 10 March 2021. Retrieved 3 April 2021.
  9. ^ InterGen & CS Energy Open US$800 MLN Australian Power Project. AsiaPulse News. 05-JUL-2001 Retrieved 2008-05-18
  10. ^ Australia joins the supercritical ranks: although a country with a coal-based power industry, Australia has taken up supercritical technologies surprisingly late. However, once started there seems to be no stopping. Here we look at a series of new supercritical developments that have been commissioned in the coal country of Queensland. Modern Power Systems 01-APR-2005 Retrieved 2008-05-18
  11. ^ Carabott, Mike (2 June 2021). "Callide C power station to be repaired for $200 million". Leading Edge Energy. Archived from the original on 11 July 2021. Retrieved 22 January 2022.
  12. ^ Callide C Archived 26 July 2011 at the Wayback Machine. Carbon Monitoring for Action. Retrieved on 23 November 2008
  13. ^ "National Pollutant Inventory". www.npi.gov.au. Archived from the original on 20 May 2017. Retrieved 5 May 2017.
  14. ^ Parkinson, Giles (3 June 2021). "Queensland coal generators tripped off like dominoes after Callide explosion". RenewEconomy. Archived from the original on 14 August 2021.
  15. ^ "Queensland power outage leaves hundreds of thousands in dark". 25 May 2021. Archived from the original on 25 May 2021. Retrieved 25 May 2021.
  16. ^ CS Energy [@CSEnergyQld] (25 May 2021). "CS Energy has immediately acted following an incident at Callide Power Station near Biloela in Central Queensland today" (Tweet) – via Twitter.
  17. ^ "Archived copy". Facebook. Archived from the original on 22 January 2022. Retrieved 25 May 2021.{{cite web}}: CS1 maint: archived copy as title (link)
  18. ^ Leitch, David (7 June 2021). "Price explosion: Gas producers clean up as sun goes down in post Callide world". RenewEconomy. Archived from the original on 7 June 2021.
  19. ^ Hill, Joshua (2 April 2024). "Callide coal unit returns to service after multiple delays with new cooling tower". Renew Economy. Retrieved 29 May 2024.

External links

  • CS Energy page on Callide
  • Callide Coal-Fired Power Stations, Queensland, Australia
  • v
  • t
  • e
Proposed power stationsCoalGas/keroseneMajor hydroMinor hydro
Wind farmsSolar power stationsCompaniesRegulatorsMarket operatorHistorical